NEC 690.12 Rapid Shutdown 30-Second Voltage Rule
Core Question: What are the legal electrical safety requirements for Rapid Shutdown on rooftop solar installations?
Executive Technical Summary
Rapid Shutdown mandates that when building main power is disconnected, rooftop DC voltage must drop to safe touch levels within 30 seconds to allow firefighters safe roof access.
Detailed First-Principles Explanation
Module-level power electronics (MLPE) like microinverters (Enphase) or DC optimizers (SolarEdge, Tigo) satisfy this requirement natively by shutting off DC string voltage at the individual panel junction.
Traditional string inverters without module-level rapid shutdown receivers cannot legally be installed on residential buildings in the United States and jurisdictions adopting NEC 2017/2020/2023.